S.N Project Name Location Client Date Work Accomplished
1 Betan Karnali Electric Project (688 MW) Acham District NEAEC 11/1/2018 7/1/2020 Exploratory core drilling (a total of 744.00m, max depth 120.00m)
2 Kimathanka Arun Electric Project (450MW) Sankhuwashaba District NEAEC 6/1/2018 1/1/2021 Exploratory core drilling vertical and inclined, geological and engineering geological mapping, construction material survey, laboratory testing and analysis. (total 1525m, max 180.00m)
3 Super Tamor Hydroelectric Project (155MW) Taplejung District Crystal Power Development Pvt. Ltd. 4/1/2018 11/1/2019 Exploratory drilling, geological and engineering geolocical mapping construction material survey and laboratory test and analysis
4 400 kV Double Circuit Transmission Line Project Eastern and Central Nepal Stantec Inc., USA 1/1/2019 8/1/2019 Geological and enginnering geological mapping, drilling and testing at substation and transmission tower, geophysical investigation (ERT and SP)
5 Grid Solar and Energy Project Battar, Trishuli RISEN Energy Co. Ltd. 9/1/2018 7/1/2019 Ground improvement, soil testing, laboraoty testing and anlaysis
6 Solu Khola Dudhkoshi HEP (86MW) Solukhumbu Hydro Venture Pvt. Ltd. 5/1/2016 11/1/2016 Exploratory drilling, geological and engineering geolocical mappind construction material survey and laboratory test and analysis
7 Rasuwagadi HEP (111 MW) Rasuwa China International water and Electric Corp. 5/1/2016 8/1/2016 Exploratory drilling (total of 168.00m linear depth, max 64.00m)
8 Solu Khola Dudh Koshi Hydroelectric Project (86MW) Solukhumbu Hydro Venture Pvt. Ltd. 3/1/2013 9/1/2013 Exploratory drilling, geological and engineering geolocical mapping construction material survey and laboratory test and analysis
9 Super Trishuli Hydroelectric Project (80MW) Chitwan / Gorkha Blue Energy Pvt. Ltd 9/1/2014 11/1/2014 Exploratory drilling, geological and engineering geolocical mapping, construction material survey and laboratory test and slope stability analysis
10 Lapchi Hydroelectric Project (160MW) Dolakha NASA Hydropower (P) Ltd. 5/1/2012 8/1/2012 Feasibiligy study, Geological mapping
11 Tamakoshi I Hydroelectric Project (100MW) Ramechhap Satyam Urja Pvt. Ltdl 6/1/2011 9/1/2011 Exploratory drilling
12 Likhu IV Hydroelectric Projects (120MW) Okhaldhunga Green Venture (P) Ltd 3/1/2011 7/1/2011 Geological and geotechnical investigation drilling works at headworks, surge tank and power house site
13 Lower Solu Hydropower Project (82 MW) Solukhumbu Essel-Clean Solu Hydropower Pvt. Ltd. 12/1/2010 5/1/2011 Exploratory drilling, Geological and enfgineering geological mapping, construction material survey, Laboratory testing and analysis
14 Likhu 1 Hydroelectric Project (77 MW) Solukhumbu Pan Himalayan Energy (P) Ltd. 11/1/2009 7/1/2010 Exploratory drilling, Geological and engineering geological mapping, construction material survey, Laboratory testing and analysis
15 Likhu 2 Hydroelectric Project (55 MW) Solukhumbu 11/1/2009 7/1/2010 Exploratory drilling, Geological and engineering geological mapping, construction material survey, Laboratory testing and analysis
16 Likhu A Hydroelectric Project (51 MW) Solukhumbu Numbur Himalay Hydropower (P) Ltd. 11/1/2009 7/1/2010 Exploratory drilling, Geological and engineering geological mapping, construction material survey, Laboratory testing and analysis
17 Upper Karnali Hydroelectric Project (900 MW) Dailekh - Achham GMR 12/1/2008 12/1/2009 Exploratory core drilling, in situ testing,derivation of soil/rock engineering properties